Stage 3 - Tender
Stage 3 - Tender
01. - TENDER DOCUMENTATION
The production of the drawings and specification from which the project will be built:
Client input is required at this time to progress the detailed design of the project
All materials, finishes, fittings, fixtures and the like must be decided at this time
A Bill of Quantities might be required to quantify all elements of the project
Drawings and specifications from the structural engineer and other specialists will be required at this time
The Client must sign off the tender documents prior to tender issue
Review timetable for Construction
02. - BASELINE TENDER DRAWINGS
Existing plans
Demolition
General arrangement drawings of site layout floor plans, elevations & sections with finishes & details
Mechanical (plumbing) layout of floor plans
Electrical layout of floor plans
Window and door schedule internal and external
Kitchen layout only (kitchen detail NOT included)
Bathroom layout (included on our Comprehensive package)
03. - TENDER RETURNED
The tender documents are sent to a number of building contractors and specialist contractors to price
On return of tenders the tenders are assessed and the contractor / contractors selected. The lowest contractor is not always the one chosen
At this stage any minor variations to the tender documents are clarified and included with the contract
The building contract for the project is signed.